Thursday, 21 March 2019

April - May 2019 - Task Plan



I.              I       First Fit Plumbing-Frappat
II.        First Fit Electrics- Frappat
III.        GR Windows Fitted – SAS Adams
IV.        GR Door Fitted       - SAS Adams
V.        Fix Oak Edge to Landing ceiling
VI.        Render Internal Walls
VII.        Render Back GR Wall Internal
VIII.        Line GR Alcove Wall, Insulate and Partition
IX.        Plasterboard ½ Partition Wall
·       Loo
·       Wardrobe Bed 1 and 2
·       Under stairs
X.        Shower Side Walls
XI.        Level Ceilings – Upstairs
XII.        Level Ceilings - Downstairs
XIII.        Hang Utility GR Door
XIV.        Hang Salon GR Door
XV.        Lift Plasterboard Upstairs