Wednesday 11 November 2020

Autumn 2020 Visit Work

I arrived at end October before the France Covid Lockdown came into effect and had fortunately preorder with Gedimat to deliver materials needed during w/c 2nd November.  They delivered without an issue on Monday 2nd and this allowed me to commence work without delay.

I had prepared the following Work Tasks to convert the Loft into a usable space:

·      Remove Old Floor Insulation

·      Clean Floor

·      Wood Treatment on Floor and Roof

·      Create Loft Floor Door Frame

·      Build Loft Door and Insulate

·      Run Electric Cables for Wall Sockets

·      Run Electric Cables for Roof Downlighters

·      Line Perimeter Back + Front Walls 14x0.6m Insulated PB

·      Line Side East * West Apex Walls Insulated PB 21sqm

·      Plasterboard Stairs Wall West Side

·      NorthEast Corner Store Rooms Stud Frame

·      Plasterboard + Insulate NE Corner Store Room

·      Fix 2xDoors & Frames 800x2000

·      Insulate Roof 21sqm

·      Plasterboard Roof 21sqm

·      Render both Chimney Breasts

·      Floor Sanding and Staining

·      Spray Paint Plasterboard

·      Install Light Switches

·      Install Downlights

·      Install Power Sockets

·      Fit Skirting Board

 WeekEnding 8th November

Here are some snaps of the work progress during the week:

I had already ordered the doors and frames from Lapeyre and as before created the partition framing around the three doors that will allow the loft to be accessed from tbe stairs and create a Store Room, as well and as a Utilities Room for the electric fuse panel, bathroom water heater and Sun Tunnel.

The doors are square and opened without adjustment, so once the ceiling is completed the framing to plasterboard will be added.

I had a lot of Tyvek House Wrap left from previous work and to avoid the insulation touching the roof tiles and to create a 25-30mm air flow space and vapour barrier, I used the wrap across the vertical roof beams 

Weekending 15th November 2020
Having completed the fixing of the Tyvek, spent the week securing the SuperFoil40 insulation across the sloping roof and securing with horizontal Chevrons to the main vertical beams and then additional vertical Chevrons that would provide the support for plasterboard and additional vapor gaps.
The SuperFoil has 37 layers of foil and insulation to protect against the cold and heat.  it was easy to install, but needed sharp scissors and a knife to cut and then sealed with foil tape and stapled on the edge to keep in place until the chevrons are applied.

Weekending 22nd November 2020
Having completed the fixing of the Tyvek, spent the week securing the SuperFoil40 insulation across the sloping roof and securing with horizontal Chevrons to the main vertical beams and then additional vertical Chevrons that would provide the support for plasterboard and additional vapor gap.

I also create a structure for a central ceiling for downlighters than would allow the A-Frame Structure to be exposed and for extra ceiling insulation supported.  Additionally, I cut 10 Insulation boards in half and 30 plasterboards to be able to lift them up into Bedroom 3 in advance of finally lifting them into the loft!

In advance of plasterboarding, I installed the sheathed electric cable runs for lighting, radiators and sockets.  Despite initially forgetting, I installed the light switch cables eventually as well!

Weekending 29th November and 6th December
Having completed the insulation and support structure the next two weeks involved securing Insulation Board to the stone walls on both chimney said Apex Walls and the low front and back walls.  Then securing plasterboard to the both front and back roofs and the flat ceiling.









                          Le Grenier Video