 Friday 18th February 2022

Pleasingly, the task of cutting all the Insulated PB for both Gable Ends Upstairs was completed today and I have it all in position.  Need to clear the remnants of boarding tomorrow and then on Monday will mix the boarding adhesive and start fixing all the cut boarding both sides.   It will probably take 3/4 bags and 2 days to adjust and fix. 

West Gable End
East Gable End



     









Once completed, I will start on cutting the board for the downstairs, which hopefully will be easier and use full boards, cut and install vertically and then the ceiling in between the beams.