Monday 21 February 2022

La Studio - Upstairs Boarding Fixed

 Monday 21st February 2022  

As hoped, I managed to complete the fixing of the Insulated Plasterboard to both West & East Gable Ends today and used 2x25kg bags of the Gedimat Adhesive.

See Pictures Below

I managed to finish in time to tidy up and get a shower before Francis from SAS Adam came as agreed to take the final measurements for me to order the Door and Large Windows.  So there will be a Front Door, glades to within 30cm of the bottom and a pair of doors at the back to allow access to an eventual patio.  The small East Side Door will now be a top opening Window, as well and an East Gable End Window to let plenty of light in upstairs.  Hopefully, these will be delivered in May for fitting.

So tomorrow, I should be able to get the upstairs low walls boarding fixed.


Tuesday 22nd February 2022

Today, I completed the fixing of the Upstairs Lower Wall Insulated PB, that took 1.5bags of the Gedimat Adhesive.  Some of the first batch went off before I had finished, but the second batch of a 1/2 bag was enough.

East Back Boarding
East Front Boarding







West Back Boarding

West Front Boarding

The task for tomorrow is to cut the Insulated Plasterboard for the downstairs exterior walls.  This should be reasonably straightforward, using full width boards cut to 1.9m high.